icon-electricity Electricity generation licence application – Port Pirie Solar Pty Ltd

  • Project Released: 19 Oct 2018
  • Project Closes: 12 Jun 2019
  • Contact: Julie Dixon

Overview

The Commission has received an application from Port Pirie Solar Pty Ltd for an electricity generation licence for the operation of a 4.9 megawatt solar generating plant, located at Murray Bridge.

Status

Current status is Final

  • Initiate
  • Submissions
  • Final

Final

 
On 12 June 2019, the  Commission issued an electricity generation licence to Port Pirie Solar Pty Ltd for the operation of a 4.9 megawatt solar generating plant, located at Murray Bridge.
 
The Commission undertook a round of public consultation in relation to the application and received no submissions from stakeholders.
 
The Commission assessed Port Pirie Solar Pty Ltd’s application for an electricity generation licence against the relevant provisions of the Electricity Act 1996 and the Essential Services Commission Act 2002 and determined that all relevant criteria under those Acts have been satisfied. It has therefore approved the application.
 
A copy of the Port Pirie Solar Pty Ltd licence may be accessed below.