Licence applications

Wind farm

 
How to apply for a licence 

Entities wishing to apply for a South Australian electricity licence should read Advisory Bulletin No 4/8 which outlines the procedure for the issuing of licences. To apply, entities must complete and submit a separate application form (refer below), for each type of licence that is being sought from the Commission. 

Following receipt of a complete application and the payment of the application fee (as applicable), the Commission will conduct public consultation of a minimum of four weeks. The Commission will consider any submissions received and where appropriate, seek further information from the applicant to inform its assessment of the application. Applicants should allow 12 weeks for a completed licence application to be assessed.

Please note that, if an incomplete application is submitted or if further substantiating information is required, the Commission will seek further information from the applicant. The 12 week assessment process will only commence once all relevant information has been provided. You are therefore encouraged to contact the Commission at an early stage to understand any information requirements which may be relevant to your application.

For information on the fees applicable to the licence refer to licence fees.

Further information for generators

The Commission seeks advice from the Technical Regulator and Australian Energy Market Operator (AEMO) when considering an application for a generation licence. Applicants must demonstrate compliance with the Technical Regulator's and AEMO’s technical requirements, prior to the issue of a generation licence.

The Technical Regulator advises the Commission on whether the generating plant suitable for the South Australian network and may suggest the inclusion of additional licence conditions to maintain system security. Further, the Technical Regulator also requires developers to include power system security services as part of their South Australian-based projects and has released a guideline specifying the technical requirements that generators above 5 megawatts must meet before seeking development approval.

AEMO is responsible for registering applicants a Generator in the National Electricity Market, or granting exemption from registration, in accordance with the National Electricity Rules (Rules). Applicants must confirm to AEMO that they meet the technical requirements set out in the Rules. Further, applicants must demonstrate to AEMO that they can meet the Commission’s 2017 model licence conditions for generators.  The Commission seeks AEMO’s advice on each generators ability to comply with these requirements.

Application Forms

Retail:
Generation:
Transmission or distribution:

 

Related Projects

Project Status
icon-electricity SA Power Networks 2020 reliability standards review Submissions
icon-electricity Electricity licence variations - Cowell Electric Supply Initiate
icon-electricity Electricity generation licence application - Electrolux Home Products Pty Ltd Initiate
icon-electricity Variation to electricity generation licence – EDL Group Operations Pty Ltd Final
icon-electricity Electricity generation and distribution licence application - EN Project Company One Pty Ltd Initiate
icon-electricity Electricity generation licence application – Peterborough Solar Farm Pty Ltd Final
icon-electricity Electricity distribution code clarification Final
icon-electricity Electricity generation licence application – Lincoln Gap Wind Farm Pty Ltd Submissions
icon-electricity Electricity generation licence application - Scentre Shopping Centre Management (SA) Pty Ltd Final
icon-electricity Electricity generation licence application – Greentricity Pty Ltd Initiate

More Projects

Related Publications

icon-electricity

Electricity distribution licence variation application - Cowell Electric Supply

icon-electricity

Electricity generation licence application - Electrolux Home Products Pty Ltd

More Publications