The Commission has amended clause 2.10.2(d) of the electricity transmission
code, with effect on and from 1 July 2011
Status
Current status is Final
Final
The Commission has amended clause 2.10.2(d) of the
electricity transmission code, with effect on and from 1 July 2011. The
amendment requires ElectraNet to effect the repair or replacement of a failed
transformer should failure occur in the Adelaide Central Area as soon as
possible to prevent the likelihood of an interruption as a result of the failure
of any other transformer (after January 2012) or of any equivalent transformer
capacity utilised by ElectraNet to meet the exit point reliability standards for
that area as mandated by the electricity transmission code.