ESCOSA content iconElectricity generation licence application – University of South Australia

  • Project Released: 5 Apr 2019
  • Project Closes: 12 Jun 2019
  • Contact: Rebecca Millwood

Overview

The Commission has received an application from the University of South Australia for an electricity generation licence to operate:

a 279.3 kilowatt solar generating plant, located at the City West Campus, Adelaide, and 
a 1.6 megawatt solar generating plant located at the Mawson Lakes Campus, Mawson Lakes.

 

Status

Current status is Final

  • Initiate
  • Submissions
  • Final

Final

On 12 June 2019, the Commission  issued an electricity generation licence to University of South Australia to operate:

a 279.3 kilowatt solar generating plant, located at the City West Campus, Adelaide, and 
a 1.6 megawatt solar generating plant located at the Mawson Lakes Campus, Mawson Lakes.

The Commission undertook a round of public consultation in relation to the application and received no submissions from stakeholders.

The Commission assessed University of South Australia’s application for an electricity generation licence against the relevant provisions of the Electricity Act 1996 and the Essential Services Commission Act 2002 and determined that all relevant criteria under those Acts have been satisfied. It has therefore approved the application.

A copy of the University of South Australia licence may be accessed below.