ESCOSA content iconElectricity generation licence application – The Corporation of the City of Adelaide

  • Project Released: 12 Dec 2019
  • Project Closes: Apr 2020
  • Contact: Deborah Hoffmann

Overview

The Commission has received an application from The Corporation of the City of Adelaide for an electricity generation licence to operate generating plant at the following locations:

  • 177.6 kilowatt solar PV generating plant located at London Road Depot
  • 261 kilowatt solar PV generating plant located at Topham Mall Upark, and
  • 409.86 kilowatt solar PV generating plant at Adelaide Aquatic Centre.
 

Status

Current status is Final

  • Initiate
  • Submissions
  • Final

Final

On 23 April 2020, the Commission issued an electricity generation licence to The Corporation of the City of Adelaide to operate generating plant:

185 kilowatt solar PV generating plant located at London Road Depot
261 kilowatt solar PV generating plant located at Topham Mall Upark, and
410 kilowatt solar PV generating plant at Adelaide Aquatic Centre.

The Commission undertook a round of public consultation in relation to the application and received no submissions from stakeholders.

The Commission assessed The Corporation of the City of Adelaide’s application for an electricity generation licence against the relevant provisions of the Electricity Act 1996 and the Essential Services Commission Act 2002 and determined that all relevant criteria under those Acts have been satisfied. It has therefore approved the application.

A copy of The Corporation of the City of Adelaide’s licence may be accessed below.