Overview

The Commission has received an application from Cornerstone College Inc for an electricity generation licence to operate a 198.8 kilowatt (kW) solar generating plant located at Mount Barker. 

Status

Current status is Final

  • Initiate
  • Submissions
  • Final

Final

The Commission issued an electricity generation licence to Cornerstone College Inc for the operation 198.8 kilowatt (kW) solar generating plant located at 68 Adelaide Road, Mount Barker.

The Commission undertook a round of public consultation in relation to the application and received no submissions from stakeholders.

The Commission assessed Cornerstone College Inc application for an electricity generation licence against the relevant provisions of the Electricity Act 1996 and the Essential Services Commission Act 2002 and determined that all relevant criteria under those Acts have been satisfied. It has therefore approved the application.

A copy of the Cornerstone College Inc licence may be accessed below.